What are the requirements for installing building templates in winter?
Before installation of the column formwork, the side line of the axis column must be flexed and the elevation must be set on the steel reinforcement. In addition to ensuring the firmness and stability of the column formwork and support, the upper and lower formwork should also be supported on the same vertical centerline. For construction in winter, the ice, snow and soil on the formwork should be cleaned up before the formwork is used, and the sundries, ice and snow in the formwork must be cleaned up after the formwork is completed, and no watering is allowed. In case of windy weather (above level 5), the assembly and hoisting of large formwork is not allowed.
The back of the wall and column formwork can be pasted with a 50mm thick flame-retardant polystyrene board for insulation, and the relative gap of the insulation board is increased by 1~2cm to ensure that the insulation board does not fall. At the same time, the outside should be sealed with bamboo glue board or three plywood. And the bamboo plywood or three plywood should be disassembled and assembled at the same time as the template.
The beam side form should be made of 18mm thick multi-layer board; the beam bottom form should be 50mm thick pine planed; the floor formwork should be seven plywood or 18mm thick multi-layer board. The support formwork should be erected in accordance with the requirements of the formwork plan, and the support elevation and arching height should be checked after the erection is completed, and the slab formwork should be laid flush to the outer opening of the beam side form, and shall not be laid on the beam side form. Key points for the demolition of building formwork: When the formwork is to be demolished in winter, the demolishing application should be submitted in accordance with the regulations, and the pressure test report of the demoulding test block should be included. The formwork can only be demolished after the demolding application is approved.
The correct order and method of template removal should be selected according to the requirements of template design. If there is no specific requirement, it should be carried out according to the principle of first supporting and then removing, and the non-load-bearing parts of the template should be removed first, and then the load-bearing parts of the template.
In a positive temperature environment, if the edges and corners and surface layer of the concrete are not damaged due to the demolding of the wall, the mold can be demolished; and in a negative temperature environment, the compressive strength of the demoulded test block should reach 4MPa and the concrete has not been affected. Moulds can be dismantled under freezing conditions, and the dismantling time should be strictly controlled. When the temperature difference between the concrete and the external environment is greater than 20°C, the surface of the concrete should be covered with polyethylene plastic sheet after the mold is removed, and the surface should be temporarily covered with a straw bag to cool it slowly.